NREGA
Implementation monitoring update
|
Table 1: Total works progress
during August-October
Table 2: Preferred works:
Progress trend during August-October 2006
Table 2.1:Percentages break up
of preferred works to total works
Table 3: State trends
Table-1 :Total works progress during
August-October 2006
On overall work-wise progress, NREGA has registered around 14 percent
growth in the last two months. As expected, the rise in the number of
completed works has been the maximum at 21.75 percent growth.
Source: Based on Ministry of Rural Development data.
Table-2: Preferred works: Progress trend
during August-October 2006
During August-October number of works in water conservation has
registered the least growth in comparisons to other preferred works
under the NREGA.

Source: Based on Ministry of Rural Development data.
Table 2.1 :Percentages break up of
preferred works to total works
Though there has been increase in the number of works under water
conservation, in comparison to total number of works under the NREGA it
has come down by around 3.5 percent. In all other components, there is
marked increase. But the trend of flood control and drought proofing
remain the least two preferred works.
Table –3 State Trends
As in August, the trend of few states accounting for large chunk of
water conservation works continues. Ten states contribute 96.17 percent
of total water conservation works. Interestingly, MP, AP and Jharkhand
alone account for 73.77 percent of total works in water conservation.

Source: Based on Ministry of Rural Development data.
|